variance-analysis

/variance-analysis

Explains budget-vs-actual or period-over-period variances: sets a materiality threshold first, builds the variance table in dollars and percent, decomposes drivers (price, volume, mix, timing, one-offs), draws a bridge waterfall, and writes the so-what per material line with forecast impact. Use when the user says 'why are we over budget', 'explain the miss vs plan', 'build the monthly flux commentary', or 'what drove the revenue variance'.

Repository
claude-inc ↗
Licence
MIT
Last repository change
22.10.2026

Assessment and security

100/ 100Class: good
Format25 / 25
Frontmatter with name and description, valid name, description up to 1,024 characters, name matching the folder.
Discoverability25 / 25
Description explains when to use the skill, has a reasonable length and uses third person.
Content35 / 35
At least 150 words and at most 500 lines, headings, step lists, examples or code.
Hygiene15 / 15
No placeholders such as TODO, no Windows paths, with a licence.
Riskno signals detected in the scan
Files in this package
1
Scripts
0
HTML comments
0
URLs in SKILL.md
0
Deprecation

No signals detected. Repository changed on 22.10.2026, without references to retired models or APIs.

Licence

MIT, open: use and modify while retaining author attribution.

What it does and when to use it

Explains budget-vs-actual or period-over-period variances: sets a materiality threshold first, builds the variance table in dollars and percent, decomposes drivers (price, volume, mix, timing, one-offs), draws a bridge waterfall, and writes the so-what per material line with forecast impact. Use when the user says 'why are we over budget', 'explain the miss vs plan', 'build the monthly flux commentary', or 'what drove the revenue variance'.

Triggers from the description

why are we over budgetexplain the miss vs planbuild the monthly flux commentarywhat drove the revenue variance
Original author description

Explains budget-vs-actual or period-over-period variances: sets a materiality threshold first, builds the variance table in dollars and percent, decomposes drivers (price, volume, mix, timing, one-offs), draws a bridge waterfall, and writes the so-what per material line with forecast impact. Use when the user says 'why are we over budget', 'explain the miss vs plan', 'build the monthly flux commentary', or 'what drove the revenue variance'.

How it works

  1. When to use
  2. Workflow
  3. Output format
  4. Quality bar
  5. Example
Original SKILL.md headings · 69 lines, 634 words
SKILL.md preview
---
name: variance-analysis
description: "Explains budget-vs-actual or period-over-period variances: sets a materiality threshold first, builds the variance table in dollars and percent, decomposes drivers (price, volume, mix, timing, one-offs), draws a bridge waterfall, and writes the so-what per material line with forecast impact. Use when the user says 'why are we over budget', 'explain the miss vs plan', 'build the monthly flux commentary', or 'what drove the revenue variance'."
---

# Variance Analysis — Variance Analyst

> "Explain the variances."

## When to use

- Budget vs actual needs explaining — "why is opex 30% over plan?".
- Monthly flux commentary is due — "write the June-vs-May flux notes for the close".
- One line moved hard — "what drove the gross margin drop?".
- Leadership wants the story — "the board asks: are we beating plan, and why?".
- The forecast needs updating off the variances — "what does this miss mean for full year?".

## Workflow

1. **Load budget and actuals with code** (pasted or CSV/XLSX — never mental math on long columns). Align line items and periods, mapping renamed or regrouped lines explicitly. Verify both columns foot to their reported totals before analyzing.
2. **Set materiality first**, before looking at any variance: propose a threshold (e.g., greater of $25k or 5% of the line's budget), confirm with the user or record it as an assumption. This prevents cherry-picking.
3. **Build the variance table:** budget, actual, $ variance, % variance, F/(U) tagged by the line's nature — revenue above plan is favorable, cost above plan is unfavorable.
4. **Split material from immaterial.** Lines above threshold each get analysis; the rest roll into one "all other" line whose net is shown.
5. **Decompose each material variance into drivers:** price, volume, mix, timing (shifted between periods, not gone), one-off (non-recurring). Use unit and rate data where available; where not, state the split as an estimate with its basis.
6. **Build the bridge waterfall:** budget total → one bar per driver → actual total, as a text waterfall (or chart if plotting is available). Bars must sum exactly to the total variance — no plug bar.
7. **Write the "so what" per material line:** root cause, whether it persists, and the action it implies. One tight paragraph each — no restating the table in prose.
8. **Note forecast impact:** classify each material variance run-rate (annualize it) vs one-time (exclude it), and state the resulting full-period outlook adjustment.

## Output format

```
# Variance Analysis — <scope> — <period> vs <baseline>
Materiality: greater of $<X> or <Y>% of line budget

## Variance table
| Line | Budget | Actual | Var $ | Var % | F/(U) | Driver summary |
|------|-------:|-------:|------:|------:|:-----:|----------------|
| <line> | | | | | | <price/volume/mix/timing/one-off> |
| All other (below threshold) | | | <net> | | | n/a |
| **Total** | | | <T> | | | |

## Bridge (budget → actual)
Budget                       <B>
  <driver 1, e.g. Volume>    −<amt>
  <driver 2, e.g. Price>     +<amt>
  <driver 3, e.g. Timing>    +<amt>
  <driver 4, e.g. One-off>   −<amt>
Actual                       <A>
Check: bars sum to total Var $ <T> ✓

## Commentary (material lines)
**<Line> — <Var $> <F/(U)>.** <root cause; persists or not; implied action.>

## Forecast impact
Run-rate: <lines → annualized effect>. One-time: <lines>. Outlook: <adjustment>.
```

## Quality bar

- [ ] Materiality stated before analysis and applied consistently.
- [ ] Table computed in code; line variances re-foot to the total variance exactly.
- [ ] Waterfall bars sum to the total — no unexplained plug.
- [ ] Every driver split labeled data-based or estimated (with basis).
- [ ] F/(U) orientation correct by line nature — a cost underspend reads favorable.
- [ ] Commentary says why and what next, not a prose restatement of the table.

## Example

**Invocation:** "`budget-q2.xlsx` vs `actuals-q2.xlsx` — why did we miss?"
**Produced:** Variance table across 28 lines at $25k/5% materiality; four material lines; a waterfall showing revenue −$180k split into volume −$210k and price +$30k; one-paragraph commentary per line; a forecast note cutting full-year revenue $150k for the run-rate volume shortfall while excluding a one-off $25k credit.

*Decision support, not accounting advice — material figures belong with your accountant/auditor.*

Versions

RepositoryScoreLicence
This page · alebgl77/claude-inc100MIT
fabioannovazzi/app_files100AGPL-3.0
fabioannovazzi/app_files100AGPL-3.0
davekilleen/Dex100MIT
anthropics/knowledge-work-plugins100Apache-2.0
sandbaseai/sandbase-skills100Apache-2.0
rongxinzy/rongxinai90AGPL-3.0
GAJETOso/financeskills90MIT
criptogus/agent-evolve-network86Apache-2.0

Database snapshot: 13.11.2026 · package version a43d7c456d5f (SHA-256 digest of the entire package)

Downloads in the last 30 days: 0 · ranking

Report a problem with this skill: harmful content, incorrect descriptions or an author’s removal request.

Similar skills

  • 90budget-vs-actual
    Compare actual performance with budget, quantify material variances, and explain timing, volume, price, mix, rate, and one-off drivers. Use for variance analysis.
  • 100budget-vs-actual
    Structures a budget-vs-actual variance analysis that isolates root causes - price/volume/mix decomposition, timing vs structural expense buckets, a materiality screen, and reforecast flags - instead of restating numbers. Use when someone asks "why did we miss budget", "write the…
  • 95glaw-budget
    GLAW budget & variance cycle — set a budget, measure actuals against it every period, explain the variances, and re-forecast. Wraps the deterministic glaw-budget-vs-actual tool (flags expense over-runs and income shortfalls past a threshold) and routes the narrative to…
  • 100flux-narrative
    Compute period-over-period movement between two trial balances, apply dual dollar-and-percent materiality, and draft variance explanations for a reviewer to confirm rather than write from scratch. Use this whenever the user mentions flux analysis, flux report, month-over-month…
  • 100analyze-plan-vs-actual
    Analyzes actuals against budget, forecast or prior year by line, entity and segment, decomposes variances into price, volume, mix, FX and timing where the data allows (ordering convention stated, residual shown), applies threshold-based commentary flags, and labels every driver…
  • 100budget-variance-analysis
    Analyze budget vs. actual variances, identify root causes, and recommend corrective actions. Use when an accountant or finance professional says "explain this variance", "budget vs. actual analysis", "why did we miss budget", "favorable / unfavorable variance", "price volume…