Plan a sprint with capacity estimation, story selection, dependency mapping, and risk identification. Use when preparing for sprint planning, estimating team capacity, selecting stories, or balancing sprint scope against velocity.

Repository
pm-skills ↗
Licence
MIT
Last repository change
23.08.2026

Assessment and security

100/ 100Class: good
Format25 / 25
Frontmatter with name and description, valid name, description up to 1,024 characters, name matching the folder.
Discoverability25 / 25
Description explains when to use the skill, has a reasonable length and uses third person.
Content35 / 35
At least 150 words and at most 500 lines, headings, step lists, examples or code.
Hygiene15 / 15
No placeholders such as TODO, no Windows paths, with a licence.
Riskno signals detected in the scan
Files in this package
1
Scripts
0
HTML comments
0
URLs in SKILL.md
0
Deprecation

No signals detected. Repository changed on 23.08.2026, without references to retired models or APIs.

Licence

MIT, open: use and modify while retaining author attribution.

What it does and when to use it

Plan a sprint with capacity estimation, story selection, dependency mapping, and risk identification. Use when preparing for sprint planning, estimating team capacity, selecting stories, or balancing sprint scope against velocity.

Original author description

Plan a sprint with capacity estimation, story selection, dependency mapping, and risk identification. Use when preparing for sprint planning, estimating team capacity, selecting stories, or balancing sprint scope against velocity.

How it works

  1. Sprint Planning
Original SKILL.md headings · 83 lines, 528 words
SKILL.md preview
---
name: sprint-plan
description: "Plan a sprint with capacity estimation, story selection, dependency mapping, and risk identification. Use when preparing for sprint planning, estimating team capacity, selecting stories, or balancing sprint scope against velocity."
---

## Sprint Planning

Plan a sprint by estimating team capacity, selecting and sequencing stories, and identifying risks.

### What You'll Need
| Input | Required? | Example |
|-------|-----------|---------|
| Sprint backlog or story list | ✅ Required | JIRA backlog export, list of user stories with estimates |
| Team composition and capacity | ✅ Required | 3 engineers (2 available), 1 designer (part-time), 2-week sprint |
| Current sprint velocity | 🟡 Recommended | "We typically complete 34 story points per sprint" |
| Carry-over from last sprint | ⚪ Optional | 2 stories unfinished from previous sprint |

> **Don't have everything?** Start anyway — the skill will work with what you provide and flag where richer input would improve the output.

### Context

You are helping plan a sprint for **$ARGUMENTS**.

If the user provides files (backlogs, velocity data, team rosters, or previous sprint reports), read them first.

### Instructions

### Phase 0: Context Confirmation

Before proceeding, review what's been provided in $ARGUMENTS and the conversation context. **Only ask about what's missing — don't re-ask what's already clear.**

1. **Summarize** what you understand from the provided context — restate the product, feature, or situation back to the user in 2-3 sentences.
2. **Identify gaps** — if any of the following are unclear, ask:
   - What is the sprint duration and team capacity?
   - What are the current priorities or OKRs guiding selection?
   - Are there any hard deadlines or dependencies to account for?
3. **Confirm**: _"Here's my understanding: [summary]. I plan to [brief description of what the skill will produce]. Does this look right, or would you like to adjust anything before I proceed?"_

If the user provides additional context, incorporate it. If the user confirms, proceed.

1. **Estimate team capacity**:
   - Number of team members and their availability (PTO, meetings, on-call)
   - Historical velocity (average story points per sprint from last 3 sprints)
   - Capacity buffer: reserve 15-20% for unexpected work, bugs, and tech debt
   - Calculate available capacity in story points or ideal hours

2. **Review and select stories**:
   - Pull from the prioritized backlog (highest priority first)
   - Verify each story meets the Definition of Ready (clear AC, estimated, no blockers)
   - Flag stories that need refinement before committing
   - Stop adding stories when capacity is reached

3. **Map dependencies**:
   - Identify stories that depend on other stories or external teams
   - Sequence dependent stories appropriately
   - Flag external dependencies and owners
   - Identify the critical path

4. **Identify risks and mitigations**:
   - Stories with high uncertainty or complexity
   - External dependencies that could slip
   - Knowledge concentration (only one person can do it)
   - Suggest mitigations for each risk

5. **Create the sprint plan summary**:

   ```
   Sprint Goal: [One sentence describing what success looks like]
   Duration: [2 weeks / 1 week / etc.]
   Team Capacity: [X story points]
   Committed Stories: [Y story points across Z stories]
   Buffer: [remaining capacity]

   Stories:
   1. [Story title] — [points] — [owner] — [dependencies]
   ...

   Risks:
   - [Risk] → [Mitigation]
   ```

6. **Define the sprint goal**: A single, clear sentence that captures the sprint's primary value delivery.

Think step by step. Save as markdown.

---

Versions

RepositoryScoreLicence
This page · tarunccet/pm-skills100MIT
borghei/Claude-Skills100MIT
phuryn/pm-skills100MIT
tranhieutt/software_development_department100MIT
highho/dsh-game-studio-presets96MIT
chatquill/claude-code-websites90MIT

Database snapshot: 13.11.2026 · package version 327d3ebfedb2 (SHA-256 digest of the entire package)

Downloads in the last 30 days: 2 · ranking

Report a problem with this skill: harmful content, incorrect descriptions or an author’s removal request.

Similar skills

  • 100sprint-plan-builder
    Agile Sprint planning assistant that builds actionable plans by selecting scope based on team capacity and historical velocity, breaking down stories into estimated tasks, analyzing dependencies, and balancing workloads. Triggers when a user asks for Sprint Planning, iteration…
  • 100sprint-planning
    Sprint planning — task hierarchy, story point sizing, capacity tracking, and sprint workflow. Use when planning sprints, creating tasks from tickets/docs, estimating work, or managing sprint capacity.
  • 90sprint-planning
    Produces a structured sprint plan from team availability, backlog items, and sprint goals. Use when a PM needs to plan an upcoming sprint - including capacity calculation, backlog scoping, dependency identification, and sprint plan document generation. Triggers on "plan the…
  • 90sprint-planner
    Turn a list of user stories or backlog items into a prioritized 2-week sprint plan with effort estimates and capacity check. Use when the user wants to plan a sprint, prioritize stories, or figure out what fits in two weeks.
  • 100user-story
    Use when generating user stories with acceptance criteria, or planning sprint capacity against a set of stories. Triggers on "write user stories", "create stories for this feature", "break this into stories", "sprint planning", or "story points".
  • 100sprint-planning
    Facilitates sprint planning with security debt baked in: capacity planning from rolling velocity, risk-weighted prioritization balancing feature value against security debt, commitment sizing, and a DevSecOps definition of done. For writing or refining the stories themselves,…

Feedback and reports

Your message goes to Bartosz Sokoliński. An email address is needed only for a reply. See the privacy policy.