Builds and interrogates a project schedule — logic-driven sequencing, dependency types and lags, float and the critical path, resource loading and leveling, schedule risk analysis, and measuring progress against a baseline rather than against optimism. Use this to construct a schedule, audit one you have inherited, find out why a plan keeps slipping, work out what a date change actually costs, or judge whether a reported percentage complete means anything.

Repository
headcount ↗
Licence
MIT
Last repository change
18.10.2026

Assessment and security

90/ 100Class: good
Format25 / 25
Frontmatter with name and description, valid name, description up to 1,024 characters, name matching the folder.
Discoverability25 / 25
Description explains when to use the skill, has a reasonable length and uses third person.
Content25 / 35
At least 150 words and at most 500 lines, headings, step lists, examples or code.
Hygiene15 / 15
No placeholders such as TODO, no Windows paths, with a licence.
Riskno signals detected in the scan
Files in this package
2
Scripts
0
HTML comments
0
URLs in SKILL.md
0
Deprecation

No signals detected. Repository changed on 18.10.2026, without references to retired models or APIs.

Licence

MIT, open: use and modify while retaining author attribution.

What it does and when to use it

Builds and interrogates a project schedule — logic-driven sequencing, dependency types and lags, float and the critical path, resource loading and leveling, schedule risk analysis, and measuring progress against a baseline rather than against optimism. Use this to construct a schedule, audit one you have inherited, find out why a plan keeps slipping, work out what a date change actually costs, or judge whether a reported percentage complete means anything.

Original author description

Builds and interrogates a project schedule — logic-driven sequencing, dependency types and lags, float and the critical path, resource loading and leveling, schedule risk analysis, and measuring progress against a baseline rather than against optimism. Use this to construct a schedule, audit one you have inherited, find out why a plan keeps slipping, work out what a date change actually costs, or judge whether a reported percentage complete means anything.

How it works

  1. Build it from logic, not from dates
  2. Float is the information, and the critical path is the consequence
  3. Load resources before you believe the dates
  4. Analyze schedule risk rather than adding a buffer at the end
  5. Measure progress against the baseline, not against effort
  6. Auditing a schedule you inherited
  7. Sources
  8. Never
Original SKILL.md headings · 85 lines, 762 words
SKILL.md preview
---
name: schedule-development-and-analysis
description: Builds and interrogates a project schedule — logic-driven sequencing, dependency types and lags, float and the critical path, resource loading and leveling, schedule risk analysis, and measuring progress against a baseline rather than against optimism. Use this to construct a schedule, audit one you have inherited, find out why a plan keeps slipping, work out what a date change actually costs, or judge whether a reported percentage complete means anything.
---

# Schedule development and analysis

A schedule is a model of how work connects. Most schedules in circulation are a list of dates
someone typed, which looks the same in a status deck and behaves completely differently when
anything moves.

## Build it from logic, not from dates

Every task except the first and last should be connected to something. A task with a date and no
predecessor is an assertion; a task with a predecessor is a plan, because when the predecessor
moves the task moves with it and the schedule tells you so.

- **Finish-to-start** is the default and covers most real dependencies.
- **Start-to-start and finish-to-finish** describe overlapping work honestly and are worth using
  rather than faking the overlap with an earlier date.
- **Lags** should represent something real — curing time, a notice period, a review window. A lag
  used to make dates line up is a hidden assumption.

**Hard-coded date constraints are where schedules go to die.** Each one severs the logic at that
point, so slippage upstream stops propagating and the schedule keeps reporting a date it can no
longer support.

## Float is the information, and the critical path is the consequence

Float is how long a task can slip before it moves the end date. The critical path is the chain with
none. Attention belongs there and almost nowhere else — expediting work with three weeks of float
buys nothing and consumes the same management capacity.

Two readings worth taking regularly: **near-critical chains**, which become critical after one bad
week and are where surprises come from, and **negative float**, which means the schedule is already
telling you the date is impossible and someone has not looked.

## Load resources before you believe the dates

A schedule that assumes the same three people work on five parallel tasks is fiction that will
resolve itself as a delay. Load the named constraint — the one team, the one approver, the one
environment — and level it. Leveling extends the schedule; that extension was always there, it was
just unrecorded.

## Analyze schedule risk rather than adding a buffer at the end

Durations are ranges. Running the schedule with ranges rather than single durations shows something
a buffer cannot: paths that merge. Where several chains converge on one milestone, the milestone
waits for the latest of them, so the probability of hitting the date is far lower than the
probability of any single chain hitting its own — which is why plans with many parallel workstreams
slip even when no individual stream looks late.

A buffer at the end of the plan protects the end date. A buffer in front of each merge point
protects the plan.

## Measure progress against the baseline, not against effort

Keep a baseline and compare to it, or "we are 70% done" has nothing to be 70% of.

The useful comparison is three-way: what was planned to be complete by now, what is actually
complete, and what it cost to get there. Those three answer different questions — the first two
give you schedule performance, the last two give you cost performance, and a project can be ahead
on one and badly behind on the other.

**Percentage complete on in-progress work is where reporting rots.** A task reported at 90% for
three weeks is not 90% complete. Binary reporting — not started, in progress, done — with small
enough tasks that "done" arrives often is more honest and takes less time to maintain.

## Auditing a schedule you inherited

Look for these in order, because each one invalidates everything after it: tasks with no
predecessor or successor, hard date constraints, negative float, durations longer than a reporting
period, tasks that have been 90% complete for more than one period, and a baseline that has been
re-set so often it no longer means anything.

## Sources

`references/sources.md` in this skill lists the outside authorities that settle the questions
here — what each one is authoritative for, and what you may do with it. Check them before
answering on anything they cover, and cite what you used. Most are free to read and not free
to reproduce; the use note on each is binding.

## Never

- Accept a date on a task with no logic behind it.
- Hard-code a constraint to make a date hold. It stops the schedule from telling you the truth.
- Report percentage complete on a task whose remaining work nobody has re-estimated.
- Re-baseline to make variance disappear. Re-baseline when scope genuinely changed, and say which.
Files in this package (2)
  • SKILL.md 5 KB
  • references/sources.md 1 KB

Versions

The database has no other skills named schedule-development-and-analysis.

Database snapshot: 13.11.2026 · package version d799dd4cddd1 (SHA-256 digest of the entire package)

Downloads in the last 30 days: 1 · ranking

Report a problem with this skill: harmful content, incorrect descriptions or an author’s removal request.

Similar skills

  • 90gao-schedule
    Knowledge base from the GAO Schedule Assessment Guide (GAO-16-89G, 2015). Use for building, assessing, or auditing a program's integrated master schedule (IMS): the ten best practices of a reliable schedule (capture, sequence, resource, duration, traceability, valid critical…
  • 100dependency-critical-path-analyzer
    Analyzes task and project dependency graphs to identify the critical path, surface blockers, calculate slack/float for non-critical tasks, and produce schedule risk assessments with prioritized recommendations. Accepts task lists with dependencies in various formats (CSV,…
  • 90schedule-and-critical-path
    Sequence work by dependency to find which tasks actually determine the finish date, and manage those. Use when a project has many parallel workstreams and an immovable date.
  • 90project-delivery
    Plans and delivers a single project — scope, estimation, scheduling, critical path, tracking, and recovering when it slips. Use this to plan a project, build or challenge a schedule, estimate credibly, track progress meaningfully, or recover a project that is late.
  • 95p6-weekly-update-review
    Weekly schedule update review of a P6 project: progress, finish dates, critical path, slippage against the baseline, changes since the previous update when given, progress issues and a critical look-ahead, with fixed actions (read only). Use when the user asks for a weekly…
  • 95p6-float-near-critical