managing-backlog

/managing-backlog

Manages a product backlog for a Product Owner in Scrum or SAFe - backlog refinement and health check, prioritisation with WSJF (cost of delay / job size), MoSCoW or RICE, capacity-based sprint or PI planning, PI objectives with business value, dependency and risk board (ROAM), and a Jira-ready CSV import. Includes a script that computes WSJF, fits features into the PI capacity and writes the Jira CSV. Use when someone mentions backlog, prioritisation, WSJF, PI planning, SAFe, ART, sprint planning, capacity, release plan, refinement, or wants to import a backlog into Jira.

Repository
AI-skills ↗
Licence
MIT
Last repository change
09.11.2026

Assessment and security

100/ 100Class: good
Format25 / 25
Frontmatter with name and description, valid name, description up to 1,024 characters, name matching the folder.
Discoverability25 / 25
Description explains when to use the skill, has a reasonable length and uses third person.
Content35 / 35
At least 150 words and at most 500 lines, headings, step lists, examples or code.
Hygiene15 / 15
No placeholders such as TODO, no Windows paths, with a licence.
Riskno signals detected in the scan
Files in this package
5
Scripts
1
HTML comments
0
URLs in SKILL.md
0
Deprecation

No signals detected. Repository changed on 09.11.2026, without references to retired models or APIs.

Licence

MIT, open: use and modify while retaining author attribution.

What to check before installing
  • 1 scripts in this package. Review them before installing, as Claude may execute them.

Scripts: scripts/wsjf.py

What it does and when to use it

Manages a product backlog for a Product Owner in Scrum or SAFe - backlog refinement and health check, prioritisation with WSJF (cost of delay / job size), MoSCoW or RICE, capacity-based sprint or PI planning, PI objectives with business value, dependency and risk board (ROAM), and a Jira-ready CSV import. Includes a script that computes WSJF, fits features into the PI capacity and writes the Jira CSV. Use when someone mentions backlog, prioritisation, WSJF, PI planning, SAFe, ART, sprint planning, capacity, release plan, refinement, or wants to import a backlog into Jira.

Original author description

Manages a product backlog for a Product Owner in Scrum or SAFe - backlog refinement and health check, prioritisation with WSJF (cost of delay / job size), MoSCoW or RICE, capacity-based sprint or PI planning, PI objectives with business value, dependency and risk board (ROAM), and a Jira-ready CSV import. Includes a script that computes WSJF, fits features into the PI capacity and writes the Jira CSV. Use when someone mentions backlog, prioritisation, WSJF, PI planning, SAFe, ART, sprint planning, capacity, release plan, refinement, or wants to import a backlog into Jira.

How it works

  1. 1. Clarify
  2. 2. Backlog health check (if a backlog is pasted)
  3. 3. Prioritise
  4. 4. Plan the PI or the sprint
  5. 5. Jira import
  6. 6. Output contract
  7. 7. Quality check
Original SKILL.md headings · 54 lines, 541 words
SKILL.md preview
---
name: managing-backlog
description: Manages a product backlog for a Product Owner in Scrum or SAFe - backlog refinement and health check, prioritisation with WSJF (cost of delay / job size), MoSCoW or RICE, capacity-based sprint or PI planning, PI objectives with business value, dependency and risk board (ROAM), and a Jira-ready CSV import. Includes a script that computes WSJF, fits features into the PI capacity and writes the Jira CSV. Use when someone mentions backlog, prioritisation, WSJF, PI planning, SAFe, ART, sprint planning, capacity, release plan, refinement, or wants to import a backlog into Jira.
---

# Backlog & PI planning

You act as a Product Owner in a bank's agile train. A backlog is healthy when the **top is ready, ordered by value, and fits the capacity**; the rest can stay rough.

## 1. Clarify

Ask only for what's missing: framework (Scrum or SAFe), team capacity (people, sprints, availability), the candidate items with any estimates, the deadlines (regulatory dates are fixed), and the dependencies on other teams.

## 2. Backlog health check (if a backlog is pasted)

Flag: items without a clear outcome, oversized items (> 1 sprint for stories, > 1 PI for features), duplicates, items blocked by an unnamed dependency, missing acceptance criteria at the top, enablers missing (tech debt, environments). Give the top 10 fixes.

## 3. Prioritise

Pick the method that fits:

| Method | When |
|---|---|
| **WSJF** (SAFe) | Features competing for a PI. WSJF = (Business value + Time criticality + Risk reduction / opportunity enablement) ÷ Job size, each on the modified Fibonacci scale 1, 2, 3, 5, 8, 13, 20 |
| **MoSCoW** | Fixed date, negotiate scope |
| **RICE** | Product discovery with reach data |

Score relatively: for each criterion, the smallest item gets 1 and the others are scored against it. A **regulatory deadline** raises time criticality, it doesn't skip the ranking; say so explicitly.

Use the script for WSJF and capacity (never compute by hand):

```bash
python3 scripts/wsjf.py features.csv --capacity 120 --project CARD --jira-csv jira-import.csv
```

Input CSV columns: `id, title, type, business_value, time_criticality, risk_reduction, job_size, points, depends_on, deadline`. The script ranks by WSJF, puts in-PI items whose dependencies are planned, flags items that miss their deadline, and writes a Jira CSV (Summary, Issue Type, Description, Labels, Story Points, a WSJF label) for Jira's CSV importer.

## 4. Plan the PI or the sprint

- **Capacity:** people × days × focus factor (default 80%), minus holidays and run support; keep ~20% for enablers and unplanned work, and say it.
- **PI objectives:** 3–6 committed objectives in business words, each with a business value 1–10 (set by the business owner, mark yours as proposals), plus uncommitted (stretch) objectives.
- **Iteration plan:** features by sprint, dependencies placed before the items that need them, the IP sprint kept free.
- **Dependencies and risks:** a board with other teams, date needed, owner. Risks are ROAMed: Resolved, Owned, Accepted, Mitigated.

## 5. Jira import

The script's CSV maps directly in Jira's *External system import → CSV*: Summary, Issue Type, Description, Labels, Story Points. Tell the user to map *Story Points* to their instance's field and to test with 3 rows first.

## 6. Output contract

1. Assumptions (capacity, scale, framework) · 2. Health check (if a backlog was given) · 3. Ranked backlog with scores and why · 4. Plan by sprint / iteration · 5. PI objectives · 6. Dependencies & ROAM risks · 7. Out of the PI and why · 8. Jira CSV

## 7. Quality check

- The plan fits the stated capacity with the buffer; every committed item has its dependencies planned earlier or flagged.
- Scores are explained in one line each; ties broken by deadline then size.
- Hand-off: top items → `writing-user-stories`; the plan to steering → `aligning-stakeholders`.
Files in this package (5)
  • SKILL.md 4 KB
  • examples/jira-import.csv 1 KB
  • examples/pi-features.csv 1 KB
  • examples/wsjf-output.md 1 KB
  • scripts/wsjf.py 6 KB

Versions

The database has no other skills named managing-backlog.

Database snapshot: 13.11.2026 · package version 429a9186ddae (SHA-256 digest of the entire package)

Downloads in the last 30 days: 1 · ranking

Report a problem with this skill: harmful content, incorrect descriptions or an author’s removal request.

Similar skills

  • 10004-backlog-prioritization
    Use when ranking an approved backlog with MoSCoW and WSJF and assigning release or sprint order; use story-mapping when the user journey and walking skeleton are not yet visible.
  • 90prioritization-frameworks
    Use when the user is prioritizing a backlog, building a roadmap, cutting scope, or arguing about what to build next. Trigger phrases include "what should we build first?", "help me cut this list", "I need to defend my roadmap", "should we do X or Y?". Surfaces the right…
  • 100rice
    Use when prioritising a feature backlog using RICE scoring (Reach, Impact, Confidence, Effort) or making a capacity-constrained prioritisation decision. Triggers on "prioritise these features", "RICE scoring", "what should we build first", "rank the backlog", or "capacity planning for the sprint".
  • 100wsjf-prioritization
    Use when sequencing backlog items, initiatives, features, epics, or projects where delay cost and job size both matter. Use when applying Weighted Shortest Job First, WSJF, Cost of Delay divided by Job Size, economic sequencing, backlog prioritization, or lean/agile prioritization.
  • 100sprint-planning
    Facilitates Sprint Planning by helping the Scrum Team craft a Sprint Goal, select Product Backlog items, and build an initial Sprint Backlog. Use when anyone says things like "let's plan the sprint", "sprint planning", "what should we work on this sprint", "help us pick stories…
  • 100sprint-planning
    Plan a sprint — scope work, estimate realistic capacity, set a goal, and draft a copy-pasteable plan. Use when you say "plan our sprint", "size the backlog", "what fits in this sprint", need a "sprint goal", are deciding "P0 vs stretch", or need to "handle carryover" from last…

Feedback and reports

Your message goes to Bartosz Sokoliński. An email address is needed only for a reply. See the privacy policy.