consult-project-plan
/consult-project-plan
This skill should be used when the user wants a phased roadmap or timeline of a cogni-consult engagement's own WBS deliverables — sequenced from the dependency graph and durations and written as an Obsidian-browsable markdown artifact. Trigger on: "project plan", "engagement timeline", "roadmap", "show the roadmap", "gantt", "gantt chart", "schedule the engagement", "when does the engagement finish", "plan the timeline", "render the project plan", or when a WBS/dashboard view hands off a request for the sequenced plan — even if the user doesn't say "project plan" explicitly. This is an interna
- Author
- cogni-work ↗
- Repository
- insight-wave ↗
- Licence
- Apache-2.0
- Last repository change
- 19.09.2026
Assessment and security
- Files in this package
- 1
- Scripts
- 0
- HTML comments
- 0
- URLs in SKILL.md
- 0
No signals detected. Repository changed on 19.09.2026, without references to retired models or APIs.
Apache-2.0, otwarta: można używać i zmieniać, z zachowaniem licencji i informacji o zmianach.
What it does and when to use it
This skill should be used when the user wants a phased roadmap or timeline of a cogni-consult engagement's own WBS deliverables — sequenced from the dependency graph and durations and written as an Obsidian-browsable markdown artifact. Trigger on: "project plan", "engagement timeline", "roadmap", "show the roadmap", "gantt", "gantt chart", "schedule the engagement", "when does the engagement finish", "plan the timeline", "render the project plan", or when a WBS/dashboard view hands off a request for the sequenced plan — even if the user doesn't say "project plan" explicitly. This is an interna
Triggers from the description
Original author description
This skill should be used when the user wants a phased roadmap or timeline of a cogni-consult engagement's own WBS deliverables — sequenced from the dependency graph and durations and written as an Obsidian-browsable markdown artifact. Trigger on: "project plan", "engagement timeline", "roadmap", "show the roadmap", "gantt", "gantt chart", "schedule the engagement", "when does the engagement finish", "plan the timeline", "render the project plan", or when a WBS/dashboard view hands off a request for the sequenced plan — even if the user doesn't say "project plan" explicitly. This is an interna
How it works
- Core Concept
- Workflow
- Important Notes
SKILL.md preview
---
name: consult-project-plan
description: |
This skill should be used when the user wants a phased roadmap or timeline of a
cogni-consult engagement's own WBS deliverables — sequenced from the dependency
graph and durations and written as an Obsidian-browsable markdown artifact.
Trigger on: "project plan", "engagement timeline", "roadmap", "show the
roadmap", "gantt", "gantt chart", "schedule the engagement", "when does the
engagement finish", "plan the timeline", "render the project plan", or when a
WBS/dashboard view hands off a request for the sequenced plan — even if the user
doesn't say "project plan" explicitly. This is an internal engagement-management
view (a read-mostly sibling of consult-dashboard and consult-resume), not a
client-facing content producer. Double Diamond phase phrasing ("discover phase",
"deliver phase timeline") refers to a legacy engagement model no longer in the
ecosystem; cogni-consult engagements have no phases — the roadmap phases here are
the derived topological layers of the deliverable graph, not engagement stages.
allowed-tools: Read, Write, Bash, Skill
---
# Consult Project Plan
Render a phased roadmap of the engagement's work-breakdown structure — when each
deliverable can start, how much effort it carries, who owns it, which points are
milestones, and which deliverables sit on the critical path — as a persisted
`project-plan.md` markdown artifact at the engagement root. It is the timeline
sibling of `consult-dashboard` (visual status) and `consult-resume` (next-action
recommender): a read-mostly view that turns the deliverable graph plus the
scheduling fields into a sequenced plan a consultant can browse in Obsidian.
## Core Concept
Schedule lives on each deliverable inside its `field.json` entry — the five
optional scheduling fields `start_date`, `due_date`, `duration`, `owner`,
`milestone` (see `$CLAUDE_PLUGIN_ROOT/references/project-plan-model.md`). A phased
timeline is **derived, never stored**: the roadmap phases are the topological
layers of the `depends_on[]` graph (layer 0 = deliverables with no in-plan
dependency; layer N = deliverables whose dependencies all sit in layers < N), and
the duration-weighted forward pass + critical path come from
`deliverable-graph.py <engagement-dir> schedule`. This skill only reads that state
and writes `project-plan.md`; it never mutates a `field.json`, never writes a
`duration`-derived date back into engagement state, and never edits a deliverable's
schedule. Populating the scheduling fields is the job of `consult-action-fields`
(the plan-editing surface), not this skill.
## Workflow
### 0. Resolve the Interaction Language
Before any user-facing output, resolve the **interaction language** — the
workspace default, overridden by the user's message language — per
`$CLAUDE_PLUGIN_ROOT/references/interaction-language.md`, which owns the
resolution ladder. Conduct the entire conversation in the resolved language.
It is independent of the engagement's `language` field, which is the
deliverable axis. This contract holds on the default path: it does not depend
on an output style being active.
The `description` of a Bash tool call is rendered to the consultant, so it is
user copy — write it in the interaction language, outcome-shaped, at most 6
words, with no script, file, or skill names, and never derived from the
script's filename or header comment. Worked pair:
`Discover cogni-consult engagements` → `Laufende Engagements holen`.
Section (f) of the canonical ecosystem register owns these five constraints —
edit them there first, then mirror into
`$CLAUDE_PLUGIN_ROOT/references/user-facing-output.md` and here.
The engagement's `language` field controls the artifact's `lang` frontmatter,
not how you address the user.
The register that output follows has two tiers. The overlay
`$CLAUDE_PLUGIN_ROOT/references/user-facing-output.md` carries this plugin's own
state lexicon, coinages and German step vocabulary, and opens with the command
that reads the canonical ecosystem register behind it — which owns scope, the
table contract, step announcements and brevity budgets, and the executive
register. Read the overlay and follow that command; table cells and headers are
user copy too, not an exemption.
### 1. Prerequisite Gate
When arriving via an in-session handoff that already resolved the engagement
directory, skip discovery. Otherwise locate the engagement:
```bash
bash $CLAUDE_PLUGIN_ROOT/scripts/discover-projects.sh --json
```
Confirm the intended engagement with the user when more than one is registered.
When discovery returns zero engagements, treat it the same as a missing
`consult-project.json`.
Read `<engagement-dir>/consult-project.json` and branch explicitly:
- If it is missing (or discovery returned zero engagements): dispatch
`Skill("cogni-consult:consult-setup")` and stop — write nothing. Setup owns
scaffolding and the knowledge-base binding.
- If `workflow_state.scope` is not `"complete"`: redirect — "Scoping isn't closed
yet — the action fields and their deliverables come from `consult-scope`." —
then dispatch `Skill("cogni-consult:consult-scope")` and stop — write nothing.
There is no plan to render until scoping has named the fields and their
deliverables.
Store the resolved engagement directory path and the engagement `slug`, `name`,
and `language` (for the artifact frontmatter). Everything below reads state only.
### 2. Read the Schedule and Deliverable State
Run the duration-weighted schedule read first — it is also the cycle gate:
```bash
python3 $CLAUDE_PLUGIN_ROOT/scripts/deliverable-graph.py <engagement-dir> schedule
```
- On `"success": false` (a cycle in the deliverable graph makes layering and the
forward pass undefined), **stop and surface the error** — report the cycle from
`data.cycles` and do **not** write `project-plan.md`. A partial plan over a
cyclic graph would be misleading. Recommend the user resolve the cycle (fix the
offending `depends_on[]` edge via `consult-action-fields`) and re-run.
- On `"success": true`, keep `data.schedule[]` (per-deliverable
`{key, action_field, deliverable, duration, earliest_start, earliest_finish,
unscheduled}`), `data.critical_path[]` (ordered keys on the longest
duration-weighted chain), `data.project_earliest_finish` (effort-days), and
`data.unscheduled[]` (keys with no valid non-negative authored `duration`).
The `schedule` read does **not** emit `owner`, `start_date`, `due_date`, or
`milestone` — read those from state. For each action field listed in
`consult-project.json`'s `action_fields[]`, read
`<engagement-dir>/action-fields/<slug>/field.json` and collect, per deliverable
entry: its `slug`, `title`, `depends_on[]` (each an `{action_field, deliverable}`
WBS coordinate), and the scheduling fields `owner`, `start_date`, `due_date`,
`milestone`. The deliverable's schedule `key` is `<action_field_slug>/<deliverable_slug>`
— join it to the matching `data.schedule[]` entry by that key.
Surface any `field.json` that fails to parse as a warning alongside the plan
rather than aborting — a plan over the readable fields is still useful. (An
unreadable field means its deliverables are absent from the schedule read too.)
### 3. Derive the Phased Roadmap (topological layers)
Compute each deliverable's plan layer from the `depends_on[]` edges collected in
Step 2. The `schedule` read has already confirmed the graph is acyclic, so
layering is well-defined:
1. Let `K` be the set of all deliverable keys `<action_field>/<deliverable>` read
in Step 2. For each deliverable, its **in-plan dependencies** are the
`depends_on[]` entries whose `<action_field>/<deliverable>` key is in `K`
(ignore any edge pointing outside the plan).
2. `layer(k) = 0` when the deliverable has no in-plan dependency; otherwise
`layer(k) = 1 + max(layer(d))` over its in-plan dependencies. This is the
deliverable's earliest phase — every deliverable in a layer can begin once its
upstream layers complete.
3. Group deliverables by layer. **Phase N** of the roadmap is layer `N-1` (Phase 1
= layer 0). Within a phase, order deliverables by `earliest_start`, then by key
for a deterministic tie-break.
A deliverable is **on the critical path** iff its key is in `data.critical_path[]`.
A deliverable is a **milestone** iff its `field.json` `milestone` is `true` — a
milestone anchors a checkpoint at its phase boundary. A milestone's only rendered
effect is the `◆` marker in the table's Milestone column and the `milestone` tag
on its gantt task; it does not alter layering or a deliverable's phase assignment.
**Empty plan (scope complete, zero deliverables).** A scoped engagement can still
carry no deliverables — Step 2 then reads an empty set and `schedule` returns empty
arrays. In that case still write `project-plan.md` (frontmatter with `phase_count:
0`), but in place of phase tables add one line noting the plan is empty until the
action fields declare deliverables, and point the user at `consult-scope` /
`consult-action-fields`. Skip the Mermaid block (no durations exist).
### 4. Render `project-plan.md`
Write `<engagement-dir>/project-plan.md` (overwriting any prior run — the plan is
derived-at-read-time, so a re-render always reflects current state). Use this
shape:
**YAML frontmatter** (Obsidian-browsable):
```yaml
---
type: project-plan
engagement: <slug>
engagement_name: <name>
lang: <language>
generated: <YYYY-MM-DD> # today's date
project_earliest_finish: <data.project_earliest_finish> # effort-days
phase_count: <number of layers>
critical_path: [<key>, ...] # data.critical_path verbatim, [] when empty
unscheduled_count: <len(data.unscheduled)>
---
```
**Body** — a short lead-in sentence (in the interaction language; see Step 0),
then one `## Phase N` heading per layer, each with a table:
| Deliverable | Action field | Owner | Start | Due | Duration (d) | Milestone | Critical path |
|-------------|--------------|-------|-------|-----|--------------|-----------|---------------|
- **Deliverable** — the deliverable `title` (fall back to its slug).
- **Owner / Start / Due** — the `field.json` `owner` / `start_date` / `due_date`,
or `—` when absent.
- **Duration (d)** — the authored `duration` (effort-days); render `—` for a
deliverable in `data.unscheduled[]` (no valid estimate), and `0` for an authored
zero.
- **Milestone** — `◆` when `milestone` is true, else blank.
- **Critical path** — `●` when the key is in `data.critical_path[]`, else blank.
After the phase tables, add a one-line **Summary**: project earliest finish
(`project_earliest_finish` effort-days), the critical-path deliverable count, and
the number of unscheduled deliverables (so the reader knows how much of the plan is
estimated).
**Optional Mermaid `gantt` block** (emit only when at least one deliverable
carries a duration, i.e. `data.unscheduled[]` does **not** cover every deliverable;
omit the whole block gracefully, with a one-line note that no durations are
authored yet, when none do):
- Use `` ```mermaid `` fenced ` gantt` with `dateFormat YYYY-MM-DD` and
`axisFormat %Y-%m-%d`, one `section Phase N` per layer, in phase order.
- Pick an **anchor date**: the earliest authored `start_date` across all
deliverables, or — when none is authored — today's date, noting in the lead-in
that dates are a relative baseline derived from the topological order.
- Each deliverable is a task: start at its authored `start_date` when present, else
`anchor + earliest_start` days (laying durations along the topological order, as
the read-model describes); length is its authored `duration` in days
(`<duration>d`), or `1d` for an unscheduled/zero deliverable so the bar renders.
Tag critical-path tasks `crit` and milestone tasks `milestone`.
- Keep task ids simple and unique (e.g. the deliverable key with `/` → `_`).
The full scheduling-field schema, the roadmap read-model, and the `schedule`
envelope live in `$CLAUDE_PLUGIN_ROOT/references/project-plan-model.md` — cite it
rather than restating it.
### 5. Confirm and Report
Tell the user (in the interaction language) that the plan was written to
`<engagement-dir>/project-plan.md`, and give a one-line takeaway: the phase count,
the project earliest finish in effort-days, and — when any exist — how many
deliverables are still unscheduled (a prompt to set durations via
`consult-action-fields` for a sharper timeline). Do not open a browser; the
artifact is markdown for Obsidian.
## Important Notes
- This skill is **read-only over engagement state** — it renders `project-plan.md`
from `field.json` schedule fields and the `schedule` read; it never modifies a
`field.json`, `consult-project.json`, or any deliverable's schedule. Populating
the five scheduling fields is `consult-action-fields`' job.
- The roadmap is **derived, never stored**: re-running the skill re-layers and
re-schedules from current `depends_on[]` and durations, so `project-plan.md` is
always overwritten to match state. No phase number or derived date is ever
written back into engagement state.
- A **cycle** in the deliverable graph makes layering and the schedule undefined —
Step 2 stops and surfaces it rather than writing a misleading partial plan.
- The roadmap **phases** are topological layers of the deliverable graph, not
engagement stages (cogni-consult engagements have no phases).
Versions
The database has no other skills named consult-project-plan.
Database snapshot: 13.11.2026 · package version ab28d6b2e877 (SHA-256 digest of the entire package)
Downloads in the last 30 days: 0 · ranking
Report a problem with this skill: harmful content, incorrect descriptions or an author’s removal request.
Similar skills
- 100consult-dashboard
Generate an interactive HTML dashboard showing a cogni-consult engagement's status — action fields, deliverables, design-thinking stage, and persona-review progress. Use whenever the user mentions dashboard, engagement dashboard, engagement status, "show me the engagement",… - 100consult-action-fields
This skill should be used when the user wants to manage the WBS of a cogni-consult engagement — listing each action field's deliverables and their status, planning a field's deliverable set, picking the next deliverable to work, adding/splitting/merging action fields after… - 100timeline-planning
Use when asked for a project timeline, schedule, sprint plan, or Gantt chart, or after breaking work into issues - converts issue estimates and dependencies into a Mermaid Gantt chart with phases, milestones, and critical path - 100timeline
Renders interactive Gantt-style project timelines and roadmaps in the browser using vis-timeline. Use when the user mentions timeline, gantt, roadmap, project plan, phases, milestones, schedule, sprints, quarters, or asks when things happen or to show a schedule. Writes… - 90local-gantt-chart-visualization-d207d3a6
Design, critique, route, and implement Gantt charts and schedule visualizations. Use when the user mentions Gantt charts, project schedules, roadmaps with task spans, milestones, dependencies, predecessors, critical path, baselines, WBS, resource plans, capacity timelines, MS… - 100backlog
Keeps a solo developer's Scrum backlog in BACKLOG.md - product goal, user stories with acceptance criteria, MoSCoW priority, WBS, weekly schedule with a Gantt chart, Definition of Done, and sprint goal, review and retrospective. Use when starting a project, planning or closing a…