close-management

/close-management

Plan and control month-end, quarter-end, and year-end close activities. Use for close calendars, dependency management, status tracking, bottleneck escalation, readiness checks, and post-close improvement.

Repository
rongxinai ↗
Licence
AGPL-3.0
Last repository change
27.10.2026

Assessment and security

90/ 100Class: good
Format25 / 25
Frontmatter with name and description, valid name, description up to 1,024 characters, name matching the folder.
Discoverability25 / 25
Description explains when to use the skill, has a reasonable length and uses third person.
Content25 / 35
At least 150 words and at most 500 lines, headings, step lists, examples or code.
Hygiene15 / 15
No placeholders such as TODO, no Windows paths, with a licence.
Riskno signals detected in the scan
Files in this package
1
Scripts
0
HTML comments
0
URLs in SKILL.md
0
Deprecation

No signals detected. Repository changed on 27.10.2026, without references to retired models or APIs.

Licence

AGPL-3.0, copyleft: przeróbki udostępniane innym muszą mieć tę samą licencję.

What it does and when to use it

Plan and control month-end, quarter-end, and year-end close activities. Use for close calendars, dependency management, status tracking, bottleneck escalation, readiness checks, and post-close improvement.

Original author description

Plan and control month-end, quarter-end, and year-end close activities. Use for close calendars, dependency management, status tracking, bottleneck escalation, readiness checks, and post-close improvement.

How it works

  1. Build the close plan
  2. Daily control
  3. Readiness gates
Original SKILL.md headings · 36 lines, 205 words
SKILL.md preview
---
name: close-management
description: Plan and control month-end, quarter-end, and year-end close activities. Use for close calendars, dependency management, status tracking, bottleneck escalation, readiness checks, and post-close improvement.
---

# Close Management

## Build the close plan

Define the close date and work backward through:

- data and subledger cut-off;
- bank, payroll, billing, payables, inventory, fixed assets, and intercompany close;
- recurring and non-recurring entries;
- balance-sheet reconciliations;
- consolidation, eliminations, currency translation, tax, and reporting;
- variance review, controller review, executive sign-off, and lock.

Each task needs an ID, entity, process, owner, reviewer, planned start/end, predecessor, required input, evidence, materiality, status, blocker, and completion timestamp.

## Daily control

1. Update status from evidence, not verbal assurance.
2. Identify critical-path delays and quantify downstream impact.
3. Escalate blocked, overdue, high-risk, and material unresolved items.
4. Prevent premature completion where entries, reconciliations, or reviews are pending.
5. Record late adjustments and assess whether the close must reopen.

## Readiness gates

- subledgers and interfaces complete;
- material entries posted and approved;
- key accounts reconciled;
- intercompany differences resolved or approved;
- statements tie and material variances are explained;
- open items are below threshold or formally accepted;
- reviewers have signed off and the ledger lock decision is recorded.

After close, compare planned vs actual duration, late tasks, late entries, recurring exceptions, and manual effort. Assign improvement actions with owners and due dates.

Versions

RepositoryScoreLicence
This page · rongxinzy/rongxinai90AGPL-3.0
alebgl77/claude-inc100MIT
anthropics/knowledge-work-plugins100Apache-2.0
GAJETOso/financeskills90MIT
sandbaseai/sandbase-skills90Apache-2.0

Database snapshot: 13.11.2026 · package version 072e7a4e1b7d (SHA-256 digest of the entire package)

Downloads in the last 30 days: 0 · ranking

Report a problem with this skill: harmful content, incorrect descriptions or an author’s removal request.

Similar skills

  • 90close-status
    Use when reporting the evidence-backed status of a named month-end or quarter-end close, its blockers, counted completion, and dependency path. Not for explaining budget variances; use variance-analysis.
  • 90month-end-close
    Run or review a month-end close: checklist, reconciliations, accruals, cut-off and sign-off. Use when the user asks to close a month or check close readiness.
  • 100month-end-close
    Use when running, planning or speeding up a month-end (or quarter-end) close — building or reviewing the close checklist and calendar, reconciling a bank statement or sub-ledger to the general ledger, writing or reviewing flux (variance) explanations, or finding why the close…
  • 100run-close-calendar
    Runs the month-end or quarter-end close calendar - tasks, owners, dependencies, workday due dates, status from the close tracker, Teams and mail, critical path, overdue and blocked items - and drafts a daily close status note. Reads and reports; never marks tasks complete or…
  • 90month-end-close-checklist-runner
    Run a disciplined month-end close: every task sequenced, evidenced and signed off. TRIGGERS - Use when user needs help with month end close checklist runner related tasks.
  • 100month-end-close-orchestrator